SESP task 1: Deadlines, priorities and a project method

This is the first page of the lesson. Read it and have a go at the activities. The rest is in the full lesson.

55 minutes

The deadline will not move

Kestrel Mutual opens its new branch on a Monday. The date is fixed. Staff, customers and a press photo are booked.

If the work is not done, you cannot ask for more time. So you plan backwards from the deadline, and you decide what comes first.

By the end of this lesson

Note

I can plan tasks backwards from a deadline and put them in priority order.

Key words

WordWhat it means
Deadlinethe date when the work must be finished
Priorityhow important a task is, so what you do first
Must havea task the project cannot work without
Should havean important task that can wait if time runs out
Could havea nice extra that you do only if there is time
Methodologya way of organising the work of a project
Waterfalla method that finishes each stage before the next starts
Agilea method that works in small steps and checks each step with the client
Networkcomputers and devices joined together so they can share data

The cells students fill in are left blank in this preview.

Starter

Have a go

Starter

3 questions
Have a go: your answers are marked here and then forgotten. Sign in if you would like your score kept, and to pick up where you left off.Sign in to keep your score

Your answers are marked here and are not kept. A college account keeps every student’s marks.

Plan backwards from the deadline

Start at the deadline. Write the last task. Work out the latest day it can start. Then do the same for the task before it.

This shows the latest start of every task. If a task starts later than that, the whole project ends late.

Worked example: latest start days

TaskDaysMust end byLatest startWhy
Test links2Day 10Day 9Days 9 and 10 are two days
Set up Wi-Fi2Day 8Day 7Testing starts on day 9, so Wi-Fi must end on day 8
Set up switch3Day 6Day 4Wi-Fi starts on day 7, so the switch ends on day 6
Run cables4Day 3Day 0Day 0 does not exist: this plan is too tight

The cells students fill in are left blank in this preview.

Check

Have a go

Check

3 questions
Have a go: your answers are marked here and then forgotten. Sign in if you would like your score kept, and to pick up where you left off.Sign in to keep your score

Your answers are marked here and are not kept. A college account keeps every student’s marks.

The lesson goes on

9 more parts of this lesson are in the full curriculum, with the tasks, the final check and the labs. A college account gives your students all of it.