Eight jobs, eight hours
You have 8 hours for the whole practice project. You have 8 jobs.
If you spend 4 hours on the first job, what happens to the rest? Many students run out of time and never finish the build.
A plan stops this. It takes 30 minutes and saves hours.
Key words
| Word | What it means | Example |
|---|---|---|
| Estimate | A careful guess of how long or how much. | Build: 120 minutes |
| Milestone | A point that shows a big step is done. | Design finished |
| Deadline | The time when the work must be finished. | 4 o'clock |
| Gantt chart | A table or picture that shows jobs against time. | rows of jobs, columns of hours |
| Risk | Something that could go wrong. | The build takes longer |
| Mitigation | What you do to make a risk smaller. | Build the must-haves first |
| Resource | Something you need for the job. | time, a computer, a tool |
| Running total | All the numbers added up so far. | 30, then 30 + 30 = 60 |
| Must-have | A part the tool needs. It must be in the tool. | book a room |
| Could-have | A nice extra part. It is only added if there is time. | a colour theme |
The cells students fill in are left blank in this preview.
Worked example: add up the minutes
| Job | Minutes | Running total |
|---|---|---|
| Read the brief | 30 | 30 |
| Make the plan | 30 | 30 + 30 = 60 |
| Find and fix defects | 60 | 60 + 60 = 120 |
| Design | 60 | 120 + 60 = 180 |
| Build | 120 | 180 + 120 = 300 |
| Test | 60 | 300 + 60 = 360 |
| Evaluate | 45 | 360 + 45 = 405 |
| Check and hand in | 15 | 405 + 15 = 420 |
The cells students fill in are left blank in this preview.
Quick check: the arithmetic
Have a go
Quick check: the arithmetic
4 questionsYour answers are marked here and are not kept. A college account keeps every student’s marks.
Try it: minutes to hours
total = 420
hours = total // 60
minutes = total % 60
print(hours, "hours and", minutes, "minutes")
# // gives the whole hours.
# % gives the minutes left over.
# Change 420 to 435 and run it again.
Gantt chart: each X is 1 hour
| Job | Hour 1 | Hour 2 | Hour 3 | Hour 4 | Hour 5 | Hour 6 | Hour 7 |
|---|---|---|---|---|---|---|---|
| Read the brief and plan (60 min) | X | ||||||
| Find and fix defects (60 min) | X | ||||||
| Design (60 min) | X | ||||||
| Build (120 min) | X | X | |||||
| Test (60 min) | X | ||||||
| Evaluate and hand in (60 min) | X |
The cells students fill in are left blank in this preview.
Always leave spare time
data-callouts.tip.label
Most jobs take more time than you think. Keep some spare minutes at the end. A plan with no spare time is a plan that fails at the first problem.